Campus lifts summer works
Thu, 15 Jun 2017 09:00:00 BST
The below campus lifts will undergo a replacement programme during the summer.
Schwann Building
Lift P04 is to undergo a replacement programme of works over the summer.
The works are programmed to start on Monday 26 June and completed on Monday 11 September.
During the works the lift will be unavailable for use.
The works should not have an impact on P03 lift which will be available for use as normal.
Queen Street Studios
Lift P061 is to undergo a replacement programme of works over the summer.
The works are programmed to start on Tuesday 4 July and completed on Monday 11 September.
During the works the lift will be unavailable for use.